The Enugu Electricity Distribution Company PLC (EEDC) has announced that there’s the gradual restoration of supply to her customers in the 5 South East States after the total system collapse.
Mr. Emeka Ezeh, Head Corporate Communications, EEDC in a statement made available to newsmen said “Awada Transmission station has been restored and our Awada, Osamala, 3-3, Army Barracks, Nnewi-Orba, and Obosi 33KV feeders and the PPI and IUNT 11KV outgoing feeders have received supply so far in Anambra State.
“Ugwuaji Transmission station has equally received supply and Gariki 33KV feeder has been restored so far.
“Also, New-Haven Transmission station has received supply and Kingsway 33KV Line 1 and Power-House 11KV outgoing feeder have been restored.
“Agu-Awka Transmission station received supply but is presently placed on station services only.”
While appealing to her customers to exercise little patience, Mr. Eze pointed out that “restoration after system collapse is gradual to avoid further collapse or challenges.
“Restoration is ongoing and we appeal to our customers in locations that are yet to be restored to be patient as all hands are on deck,” while assuring that “EEDC remains committed to delivering improved services to her esteemed customers.”